The East Bank is getting built in an order that is easy to miss. The first piece to open is the one East Nashville residents will use least on an ordinary day, which is a 60,000-ticket stadium. The pieces they would use every week come years later: a walkable street grid, a rebuilt pedestrian bridge and the boulevard that ties it all together. Between those two stages, the Victory Memorial Bridge closes for about two years.
For someone comparing homes in Edgefield, the East End and Shelby Hills, Cleveland Park, McFerrin Park or Lockeland Springs, that order matters more than how close a house is to the river. Two buyers on the same block could own very different things. One holds the house from 2027 to 2031 and lives through the construction years. The other holds it into the mid-2030s, after the drafted completion dates for the projects. Here is the schedule, year by year, built from the Metro, TDOT and East Bank Development Authority records published this fall.
2027: The stadium opens and the bridge closes
The new enclosed Nissan Stadium is the closest milestone. At the East Bank Development Authority's September 22 board meeting, the stadium team showed five months of construction remaining, with early turnover of spaces on January 7, 2027 and substantial completion on February 17, 2027. The same presentation listed demolition of the old stadium for early 2027.
The 2027 calendar is already filling up. The stadium's upcoming events page lists Noah Kahan on May 4, Zach Bryan on May 22 and CMA Fest from June 10 to 13. Kenny Chesney follows on July 3, and Morgan Wallen plays August 27 and 28. As of the stadium's October 2026 transportation guide, Titans-game parking on the stadium campus is sold out with no day-of sales, and parking for non-NFL events is limited and sold only in advance. The guide routes walkers over the Woodland Street Bridge, the Korean Veterans Boulevard Bridge and the John Seigenthaler Pedestrian Bridge.
Two of those bridges also carry East Nashville's daily car trips downtown. In summer 2027 a third car crossing, the Victory Memorial Bridge, closes. On November 12, TDOT announced the timeline for its James Robertson Parkway project. Wright Brothers, a Tennessee contractor, will lower the viaduct leading to the Victory Memorial Bridge and rebuild the parkway between Interstate Drive and South First Street, the future East Bank Boulevard. Construction begins in spring 2027. The bridge closes to cars and pedestrians from summer 2027 until summer 2029, and TDOT expects substantial completion in late 2029. TDOT's project FAQ says any bus route, stop or schedule changes will be announced in advance through WeGo.
That leaves two direct vehicle crossings into downtown. NewsChannel 5 reported in September that they would be the Woodland Street Bridge and the Shelby Avenue and Korean Veterans Boulevard Bridge. Woodland is in good shape for the extra load. Metro's transportation department lists its sidewalk, expansion-joint, drain and asphalt repairs as complete. Both remaining bridges also lead straight to the stadium, so concert nights in the summer of 2027 will put event crowds and the bridge detour on the same two crossings.
For a buyer, this changes which question to ask about a house. Whether a street is close to the East Bank matters less for the next three years than which bridge that household uses to get downtown. A home whose daily route runs over James Robertson Parkway will have a different 2028 than one that already crosses on Woodland.
2027 also brings the first walking upgrade
Some of the work happening now is meant for people on foot. NewsChannel 5 reported on November 10 that construction had started on the Seigenthaler Bridge Connector, a ramp from the pedestrian bridge down to Wasioto Park and the East Bank Greenway, with completion expected by the end of 2027. On the street grid, the authority's September report expected phases 1 and 2 of the new South Second Street, between Shelby and Woodland, to finish by the end of November 2026. Shelby Avenue utility duct-bank work was targeted for the first quarter of 2027.
Across the river at River North, Oracle's campus is still in early works. Metro's first-quarter 2026 report describes the company's planned world headquarters as $379 million invested across more than 76 acres, with 8,500 jobs expected over time. It puts the current phase at demolition and utility relocation, finishing around spring 2027. Oracle's planned pedestrian bridge from River North to Germantown was at Army Corps permitting and preliminary Metro review as of the authority's August meeting.
2028 and 2029: The middle years
New housing on the East Bank arrives while the bridge is closed. Eastpoint Flats, the Fallon Company's project at 501 South Second Street, is 323 affordable apartments with about 20,000 square feet of retail, including a daycare. Its September schedule shows groundbreaking in the second quarter of 2026, foundations complete in the first quarter of 2027, lease-up in the fourth quarter of 2028 and full completion in the first quarter of 2029. Metro's 2024 agreement with Fallon calls for 1,550 housing units across the 30-acre initial development area.
South Second Street phases 3 and 4 are scheduled for the fourth quarter of 2028. Under the authority's September plan, major construction on a separate reconstruction and extension of the Seigenthaler pedestrian bridge on the East Bank side runs through 2028 and 2029, with opening targeted for fall 2029. That work has a funding commitment capped at $75 million. If TDOT holds to its schedule, the rebuilt Victory Memorial Bridge reopens in summer 2029.
The north side of the area has a 2029 date of its own. The Marine Drive extension is meant to connect the East Bank east toward Dickerson Pike with room for multimodal travel and dedicated bus rapid transit. It was assigned up to $80 million in authority funding. Metro's first-quarter report says TDOT planned design-build delivery in 2029. For McFerrin Park and the Dickerson Pike corridor, that road matters more than anything happening next to the stadium.
2030: Super Bowl year, and a hotel that lands after it
Nashville hosts Super Bowl LXIV in 2030, and TDOT presents its bridge schedule as finishing before the game. The private schedule for the parcels next to the stadium is running later. The Nashville Banner reported on September 23 that Fallon's hotel beside the stadium is now forecast for the third quarter of 2030, after the Super Bowl. The earlier estimate had been early 2029. The authority's September plan describes it as 600 rooms with about 25,000 square feet of retail, breaking ground in the third quarter of 2027. According to the Banner, the authority asked Metro staff to convene more meetings on what could still speed things up.
TPAC's East Bank complex follows a similar timeline. Metro Council approved it in January 2026, and the draft program schedule projects substantial completion in November 2030.
2031 to 2035: The boulevard
East Bank Boulevard is the piece that ties the area into a neighborhood. Metro's concept is a north-south multimodal corridor with a dedicated transit lane in each direction. As of Metro's April 2026 quarterly report, right-of-way acquisition was underway. The draft program schedule places construction of the segment from Korean Veterans Boulevard to James Robertson Parkway in 2031 to 2033, and the segment from James Robertson Parkway to Jefferson Street in 2033 to 2035. Metro labels these dates a draft. A shorter stretch, from Victory Way to Shelby, is funded separately by Fallon under the 2024 agreement.
Reading a listing against the calendar
Laid end to end, the dates run like this. The stadium finishes in February 2027 and its first listed concert is May 4. Eastpoint Flats begins lease-up in late 2028, the Seigenthaler extension targets fall 2029, and the boulevard's drafted construction runs from 2031 to 2035. A buyer in East Nashville is choosing a home and a set of years at the same time.
In practice, that comes down to three things to settle before touring. The first is the daily route: which bridge the household uses now, and what that trip looks like from summer 2027 to summer 2029. The second is the stadium calendar, since the walking routes to it run over the same Woodland and Korean Veterans crossings. The third is how long the household plans to stay. A five-year owner who buys this winter would likely sell before the drafted boulevard dates. A ten-year owner would likely still be there for them. Our Nashville neighborhood guide and the Halloween walk through Five Points show what the corridor feels like now, before any of this arrives.
A short FAQ
When exactly does the Victory Memorial Bridge close? TDOT's November 12 announcement puts the closure in summer 2027 and the reopening in summer 2029, with substantial completion in late 2029. Proposed alternative-route maps for drivers and pedestrians are posted on TDOT's project page, and TDOT notes they may change as design advances.
Will the Seigenthaler Pedestrian Bridge stay open during the connector work? FOX 17 reported in August that organizers expected the bridge to remain open during connector construction to keep event access. The connector itself is expected to finish by the end of 2027.
Is there for-sale housing on the East Bank? The first housing project under construction there, Eastpoint Flats, is affordable apartments, with lease-up scheduled for late 2028. For now, buyers who want to own near the East Bank are looking at the established East Nashville streets on the other side of Interstate Drive.
If you are comparing East Nashville homes, I'm glad to sit down with the TDOT and East Bank schedules and go through how they line up with your daily route and how long you plan to stay. Sandra Hill has lived in Middle Tennessee since 1995, and you can start on the buyers page. Let's Connect.